Electrical preventive maintenance plan
By Daniel Serrano Armenta, industrial maintenance electrician
An electrical installation gives no warning before it fails: a loose terminal heats up for months until one day it trips the switchboard, or worse. Electrical preventive maintenance is about finding those problems first, and many countries also make some inspections mandatory. This guide covers what to check on each piece of equipment, how often, what the rules look like using Spain as an example, and how to run it all in a CMMS such as MantPro, which is free and open source.
Important: the intervals in this guide are suggestions. Legal requirements depend on the country and the type of installation, and each piece of equipment's schedule depends on its manufacturer and how critical it is to your process. Check the regulations that apply in your country; if in doubt, ask your electrical contractor or an accredited inspection body.
Example: what Spanish regulations require
Every country has its own rules. As a reference, this is what applies in Spain under the Low Voltage Electrotechnical Regulation (REBT) and related rules:
- Periodic low-voltage inspections (ITC-BT-05). Installations that required an initial inspection must be inspected by an accredited inspection body (OCA) every 5 years. They include, among others, industrial installations requiring a design project with more than 100 kW installed, premises open to the public, premises with a class I fire or explosion risk (except car parks with fewer than 25 spaces), wet premises over 25 kW, swimming pools over 10 kW, operating theatres and outdoor lighting over 5 kW. Common installations in residential buildings over 100 kW, every 10 years.
- Earthing systems (ITC-BT-18). They must be checked by technically competent staff at least once a year, when the ground is driest. Where the ground does not favour the conservation of the electrodes, the electrodes and bonding conductors are uncovered for inspection at least every 5 years.
- High voltage and private substations (Royal Decree 337/2014). Private high-voltage installations must have a maintenance contract with a licensed electrical contractor. In-house maintenance is allowed when the competent authority approves it and the owner has the necessary staff and technical means. They must also be inspected by an OCA at least every 3 years (ITC-RAT 23).
- Safe working (Royal Decree 614/2001). Work is carried out by authorised or qualified workers, depending on the type of work and the voltage. Dead working follows the five golden rules: disconnect; prevent any possible re-energisation; verify the absence of voltage; earth and short-circuit; and protect against nearby live parts and mark off the work area.
Tasks per equipment
| Equipment | What to check | Suggested interval |
|---|---|---|
| Main and sub-distribution boards | Visual inspection, cleaning, labelling, condition of enclosures and locks | Every 6 or 12 months |
| Main and sub-distribution boards | Thermography with the installation under load | Yearly |
| Main and sub-distribution boards | Check connections; re-tighten only where needed, to the manufacturer's torque and always de-energised | Based on inspection and thermography |
| Residual current devices (RCDs) | Test with the test button | Monthly or quarterly |
| Residual current devices (RCDs) | Measure trip time and trip current with a tester | Yearly |
| Earthing systems | Measure earth resistance and check connections | Yearly (mandatory in Spain, ITC-BT-18) |
| Circuits and loads | Insulation resistance test | Yearly or based on criticality |
| Power factor correction capacitor bank | Swollen or hot capacitors, contactors, fuses, controller and power factor | Every 6 months |
| UPS | Battery condition and runtime, alarms, ventilation | Every 6 months |
| Standby generator | Start-up and no-load test | Monthly |
| Standby generator | Load test, fluid levels, filters and starter batteries | Yearly or by running hours |
| Emergency lighting | Function test | Monthly, or as required by the applicable rules and instructions |
| Emergency lighting | Duration test | Yearly, or as required by the applicable rules and instructions |
| Critical motors | Temperature, vibration, current draw, insulation, bearings and ventilation | Based on criticality |
| Transformer (if you have a substation) | Temperature and connections; for oil-filled units, oil level and condition; for dry-type units, cleaning and resin condition | Yearly, with the maintenance contractor |
Apart from the earthing check required in Spain, these intervals are recommendations, not general legal obligations: adapt them to the manufacturer's instructions, your local regulations and how critical each piece of equipment is.
Thermography is one of the tasks that prevents the most failures: a hot spot on a terminal or fuse shows up long before it fails. Carry it out with the installation under representative load conditions, ideally close to its normal duty: load-related thermal anomalies can go unnoticed when the installation is running unloaded.
How to set up the plan in MantPro
1. Assets: a tree of the installation
Enter the installation as a tree: Substation → Transformer, Main switchboard → Sub-distribution boards, Standby generator, UPS, Capacitor bank… That way every measurement, thermal image or breakdown ends up in the history of the right piece of equipment. If you already have the list in Excel, you can import it.
2. Tasks: by date or by running hours
- Switchboard, RCD or earthing checks as date-based recurring alerts, with grace days.
- Statutory inspections, with their multi-year frequency: low-voltage inspection by an authorised body (OCA) every 5 or 10 years, high-voltage every 3, uncovering the earth electrodes every 5. MantPro offers every 2, 3, 4, 5 or 10 years.
- The standby generator by running-hours meter or by date, whichever comes first ("every 250 h or every year"). More in preventive maintenance.
3. Measurements: checklists with acceptable ranges
MantPro checklists support readings with their unit and acceptable range, and automatically mark an out-of-range reading as "not OK". For example:
- Earth resistance (Ω), with the maximum your installation allows.
- Insulation resistance (MΩ), with its minimum.
- RCD trip time (ms) at its rated current.
- Power factor of the capacitor bank.
- Runtime of the UPS or emergency lighting (min).
Each inspection then leaves its measurements stored with the job, with date and technician, in the equipment's history.
In the Machines tab, 📈 Readings puts each item's values together inspection after inspection: a chart with the correct-range band and out-of-range values in red, so you can see whether the earth resistance is creeping up before it goes over the maximum. Export it to PDF with your logo or to Excel, ready to show the inspection body, the insurer or the customer.
4. Photos, thermal images and reports
Attach photos of the switchboard and the thermal camera images to the job, before and after fixing the hot spot. The PDF report with your company logo documents the work and makes it easier to follow up on actions and to prepare the paperwork an inspection body, insurer or client may ask for. It does not replace official inspection certificates.
5. QR labels on the switchboards
Stick a QR label on each switchboard: the technician scans it with their phone and has its history and checklist in front of them, even with no signal in the electrical room.
Frequently asked questions
How often do installations need a low-voltage inspection in Spain?
Every 5 years for installations that required an initial inspection under ITC-BT-05 of the REBT, such as industrial installations requiring a design project with more than 100 kW installed or premises open to the public, among others. Common installations in residential buildings over 100 kW, every 10 years. Other countries set their own intervals.
How often should the earthing system be checked in Spain?
At least once a year, when the ground is driest, under ITC-BT-18 of the REBT. Where the ground does not favour electrode conservation, the electrodes must be uncovered for inspection at least every 5 years.
How often is a private substation inspected in Spain?
Private high-voltage installations must be inspected by an accredited inspection body at least every 3 years. Maintenance is contracted with a licensed electrical contractor, unless the competent authority approves doing it in-house.
What earth resistance value is acceptable?
It depends on the installation and its earthing system. In a TT system, the earth resistance multiplied by the current that trips the protective device must not exceed the conventional touch voltage limit (Ra × Ia ≤ UL). In Spain that limit is 50 V in normal conditions and 24 V in conductive locations. The design and the specific conditions of the installation determine the acceptable value.
Can I run electrical preventive maintenance with free software?
Yes. MantPro is free and open source: date-based and running-hours alerts, checklists with measurements and ranges, photos, PDF reports and an offline Android app, with no limits on equipment or users.